>

Tudor Court

Tudor Court Street and Streetscape Improvements

Stay tuned! Construction Anticipated March-July 2020

Glencoe’s Downtown Plan, adopted in December 2016, recommends the Village should reinvest in initiatives that support private property improvements and enhance the downtown district’s attractiveness and unique character. Tudor Court was specifically identified in the Downtown Plan as presenting an opportunity for place-making through special streetscape treatments. In particular, enhancements that support the emerging “arts core” thanks to Writers Theatre and surrounding galleries, were highlighted as a priority. The intention is to create public and semi-public spaces that facilitate both social and economic exchanges – places where friends gather, celebrations are held and cultures mix.

To this end, the Village enlisted the assistance of Teska Associates, an urban planning and design firm based in Evanston, to facilitate community engagement around the Tudor Court enhancements. Feedback from the community was used to identify desired design alternatives, which were presented to the Village Board for consideration in January and March 2019. The Village Board's feedback was incorporated into a final set of designs and the project was bid out in June. Since that time, the Village has contracted with Alliance Contractors and anticipates for the project to begin March 2020, with final touches carrying the project through July 2020. Learn more from the timeline below. 

Project Details

The project is planned to include the following:

  • Grinding and resurfacing of the roadway, new concrete curb and gutter and reconstructing the sidewalks, reusing the existing brick pavers where possible;
  • Realigning the roadway curb to create a designated drop off area for cars and buses, and developing a new midblock pedestrian crossing in front of Writers Theatre;
  • Enhancing the pedestrian level lighting with decorative LED bollards, and LED lighting in crosswalk pavement and planter curbs;
  • Installing new clustered seating, benches and landscaping along Friends Park, at new planter curbs and along storefronts, as well as the inclusion of additional bicycle parking near Friends Park and Writers Theatre;
  • Widening the east end of Tudor Court to accommodate festivals and events;
  • Terminating Glencoe Drive (which would become a dead-end street), allowing for the expansion and later renovation of the existing park area located between Writers Theatre and Green Bay Road (this would be a collaborative effort between the Village and Glencoe Park District);

The image below represents a rendering of conceptual improvements (click to enlarge):

tudor court streetscape

 

Design Review Timeline tudorcourt_stakeholders

  • July 18, 2017: Programming / Space Use and Analysis
    The Village created the Tudor Court Stakeholder Focus Group to help guide the process. This group was made up of representatives from several Tudor Court businesses, Writers Theatre, the Women’s Library Club, Glencoe Park District, the Glencoe Chamber of Commerce and homeowners adjacent to Tudor. Together, the Stakeholder Focus Group developed a shared understanding about issues and perceptions related to Tudor Court; the groups efforts were collaborative and focused on “big picture” items related to use, functions, activities and appearances within the right-of-way and adjacent properties. Teska conducted a workshop meeting at Village Hall Chambers. The meeting included introductions to the project team, scope and schedule. Teska’s presentation to the group included an overview of the Downtown Plan, an existing conditions assessment and comparable character photographs that illustrate enhancement features from other “special places.” Following the workshop, the group participated in a walking tour of Tudor Court.
Some general themes that arose from these activities included:
    1. Tudor Court should be a comfortable and safe environment for pedestrians first, but also accommodate cars and deliveries;
    2. Access and entrances to Tudor Court from surroundings are important (such as the Green Bay Road mid-block crossing, Park Avenue and Vernon Avenue);
    3. Passive or restful places for people should be located adjacent to active uses (such as Writers Theater, businesses and Friend’s Park);
    4. Screening of the backs of buildings may be important;
    5. In addition to being safe and functional, the objective should be to make Tudor Court attractive and celebratory of arts and culture.
  • August 30, 2017: Conceptual Models / Benchmarking
    Based on the input received in July, Teska produced three Programmatic Exercises. The exercises included interchangeable design elements and and were organized into “Levels of Intervention”. The Levels of Intervention presented included the following interchangeable design elements:
    1. Minimum Intervention: Existing roadway configuration remains intact and is resurfaced. Modest pavement improvements are made at key pedestrian crossing areas. Glencoe Drive remains in its current configuration. Site features are added to the existing right-of-way.
    2. Intermediate Intervention: Roadway and on-street parking is reconfigured to expand and protect the pedestrian space. Glencoe Drive is terminated north of the Writers Theatre/Women’s Library Club Park property line, and converted to additional green space. Site features are integrated.
    3. Maximum Intervention: Glencoe Drive is terminated, as indicated in the Intermediate Intervention. The Tudor Court Roadway is reconstructed as a shared street/plaza environment, including a conversion of all parking to parallel configuration. Site features are integrated.
  • September 19, 2017: Committee of the Whole Presentation #1
    After incorporating the Stakeholder Focus Group’s feedback into the Programmatic Exercises, they were presented to the Village Board at the September 19 Committee of the Whole meeting. 
  • November 13, 2017: Tudor Court Place-making Public Open House
    Download event flyer | Download presentation 
    Following initial input from the Board, the Village and Teska partnered with the Village to host an open house to facilitate further discussion. At the open house, three concepts were presented to for feedback; Glencoe residents and stakeholders are encouraged to attend and share their input. 

  • December 18, 2017: Stakeholder Focus Group Meeting
    Following the public open house, the Stakeholder Focus Group met to respond to community ideas and suggestions.
  • December 2017 - January 2018: Public Input Survey
    A nine-question survey was distributed throughout the community to further engage the community.
  • January 18, 2018: Committee of the Whole Presentation #2
    View Meeting Agenda Packet | View Minutes
    A presentation to the Village Board, inclusive of design concepts, public feedback and cost estimates was made at the January Committee of the Whole meeting. Read the packet linked above for more information.
  • May 15, 2018: Committee of the Whole Presentation #3
    View Meeting Agenda Packet | View Minutes
    Following Village Board feedback given at the January Committee of the Whole meeting, Village staff worked with Teska Associates to develop refined cost estimates for Tudor Court improvements. Trustees discussed future design elements and decided that memorable features were most suitable for the community moving forward. Read the packet above linked for more information. 
  • June 21, 2018: Village Board Approval of Design and Engineering Agreements
    View Meeting Agenda Packet View Minutes
    The Village Board approved two design agreements for Tudor Court street and streetscape improvements.

  • January 10, 2019: Design Alternatives - Committee of the Whole Presentation #4
    View Meeting Agenda Packet | View Minutes
    Teska Associates presented two design concepts, with one alternative representing baseline streetscape improvements, with the other representing the baseline improvements in addition to special elements. The Village Board directed staff to move forward with planning for the baseline improvements and requested additional options for various components of the special elements, such as seating and pedestrian-scale lighting. 

  • March 21, 2019: Final Design - Committee of the Whole Presentation #5 
    View Meeting Agenda Packet
    The Village Board offered feedback on the final design and instructed staff to move forward with finalizing construction plans and preparing bid documents. Tentatively, the Village plans to bring the project in late spring, and to bring a contract for construction to the Village Board in early summer. Construction could begin as early as fall 2019.