>

Village Construction Projects

CIPLogoFINAL(Small)

Current Construction Projects 

Staff has begun coordinating with contractors to complete several capital improvement projects, detailed in the Village's 10-Year Community Improvement Program (CIP). As we enter the 2018 construction season, stay tuned to the Weekly Construction Updates on this page, register for Glencoe CONNECT and subscribe to Village eNews for timely updates as these projects progress.

View the Fiscal Year 2019 CIP Project Schedule (Updated June 2018).

Construction Communication Survey

The Village is always looking for ways to improve our communication efforts, and as such, has developed a survey to gauge resident's satisfaction with our outreach during these projects. All response data will be kept anonymous and will be used to inform our future communication plans.

Should you have questions regarding this survey, please contact Management Analyst Adam Hall at ahall@villageofglencoe.org / (847) 461-1115.


Downtown Sidewalk Paver Restoration - COMPLETED

Downtown Sidewalk Paver Restoration Project Background

Fiscal Year 2019 marks the first year of a five-year Downtown Sidewalk Brick Paver Restoration Project. There is approximately 70,000 square feet of brick paver sidewalk in the downtown and this year’s program will restore 8,000 square feet on the north side of Park Avenue from Green Bay Road to Vernon Avenue. The scope of the work includes the removal of all brick pavers/border tiles, regrading of the stone sub-base and finally the resetting of the brick pavers/border tiles including the replacement of any that are stained or cracked. The Village is working with the contractor to limit the impact to businesses and patrons.

Residential Sidewalk Replacement Project - Completed

Residential Sidewalk Replacement Project Background

The Village maintains over 73 miles of public sidewalk throughout the community. Each year, the Village replaces sidewalk square areas based on the structural condition of the concrete (cracking, spalling or deterioration), heaved sections (trip hazards), excessive sloping and poor drainage. The primary goal of the program is to maintain a safe and functional pedestrian sidewalk system.

Residential sidewalk in the Village is broken into three areas and is inspected on a 3-year cycle. This year, the replacement project will be focused on Area 2 as highlighted on the map at right. The Village estimates that we will replace approximately 30,000 square feet of sidewalk this year. 

Sanitary Sewer Rehabilitation Program In Progress

Sanitary Sewer Rehabilitation Program Project Background

This year, sanitary sewer lining, sanitary manhole rehabilitation and the next phase of engineering for inflow/infiltration (I/I) compliance will occur in the area generally north of Dundee Road and west of the UP-North railroad tracks (extending somewhat further south and east in some locations as seen in the map at right).

The Village's sanitary sewer system consists of 40 miles of sanitary sewer main, 900 manholes and eight lift stations. Sanitary sewer lining is a trenchless technology that involves pulling a new liner through an old pipe. Through a process of inflating and curing the material, the pipe is rehabilitated. Lining sanitary sewer mains eliminates inflow and infiltration which contribute to charging the sanitary sewer and results in basement backups. The Village hired an engineering consultant in Fiscal Year 2018 to assist staff in selecting a targeted priority area within the Village system to perform detailed investigation through smoke testing, televising of sewer main, and physical inspections of manholes to check for (I/I). 

Notification letters have been mailed to properties that will be directly impacted by excavations and other construction related activities. 

  • Total Project Cost: $450,000
  • Project Engineer: RJN Group, Inc.
  • Project Contractor: Mauro Sewer Construction, Inc.
  • Project Start Date: October 8, 2018
  • Project Completion Date: December 7, 2018
  • Project Manager: Anna Kesler, Village Engineer
  • Resident Impacts: Temporary lane closures, Parkway restoration for impacted areas, Temporary sidewalk closures, Intermittent loss of sewer service.
  • Construction Update  - Week Of November 12: The contractor has completed all 14 sanitary sewer point repairs. Work on manhole adjustments have begun. It is anticipated that work will continue for approximately four to five weeks to complete the remaining point repairs and manhole rehabilitation work. 
  • Initial Notification Letter: View notification letter
  • Follow-up Notification Letter: View notification letter
  • Project Location Map: View location map
  • Photo Gallery: Coming soon


Whitebridge Hill Road Water Main Replacement 
In Progress

Water Main Replacement Project Background

Fiscal Year 2019 improvements to the Village’s water distribution system (water mains and service lines) includes a water main replacement on Whitebridge Hill Road east of Sheridan Road and the elimination of a section of water main on Dell Place.

These projects were identified as needing replacement and removal in 2016 as part of a Water Distribution System Study, completed by Strand Associates. Read the full study here. The study identified segments of water main for replacement based on the analysis of the existing distribution system under peak demand, water main break data, and input from Village staff. Projects are prioritized using a number of factors including the ratio of breaks per 100 feet of pipe and areas with deficient fire flow. Annual distribution system improvements will be coordinated with other Village infrastructure improvements, such as sanitary sewer, storm sewer and street resurfacing. 

  • Total Project Cost: $160,000
  • Project Contractor: Mauro Sewer Construction, Inc.
  • Project Start Date: October 15, 2018
  • Project Completion Date: November 16, 2018
  • Project Manager: Donald Kirk, General Superintendent
  • Resident Impacts: Temporary street and sidewalk closure, Short term water outage during switchover to new services.
  • Construction Update  - Week Of November 12: The contractor has completed all installation of water main and water services. This week, the contractor will work on restorations of parkway areas that were distrubed during construction. 
  • Initial Notification Letter: View notification letter
  • Project Location Map: View location map