>

Village Construction Projects

CIPLogoFINAL(Small)

Current Construction Projects 

Staff is busy coordinating with contractors to complete several capital improvement projects for 2020 as detailed in the Village's 10-Year Community Improvement Program (CIP). As continue the construction season, stay tuned to the construction updates on this page, subscribe to Village eNews for timely updates as these projects progress. 

Look here for more information on regional construction projects being conducted by other agencies. 

Tudor Court Street and Streetscape Improvements

Project Description

Following a two year public engagement and design review process, the Village is moving forward with street and streetscape improvements on Tudor Court. Learn more about the Tudor Court Design Review Process here.

The scope of the improvements will include new concrete curb and gutter, resurfaced street pavement and restoration of the brick pavers. Additional improvements will include realigning the roadway to create a designated drop-off area, a new mid-block pedestrian crosswalk, enhancements to pedestrian level lighting, new clustered seating, benches and landscaping as well as the removal of the south end of Glencoe Drive and the construction of a dead-end turnaround.

  • Total Project Cost: $1,736,375
  • Project Contractor: Alliance Contractors, Inc.
  • Project Start Date: Monday, April 13, 2020
  • Project Completion Date: August 2020
  • Project Manager: James Tigue, Civil Engineer
  • Resident Impacts: Temporary sidewalk closure and some temporary loss of street parking.
  • Initial Notification Letter: Glencoe Drive Residents; Tudor Court Business and Property Owners
  • Construction Update: All new concrete curb has been poured on both sides of the street, and the sidewalk pavers and raised landscape area curbs on the south side have also been completed. Work continues on the new retaining walls on east and west ends of the north side of the street. These retaining walls will include bench areas with embedded lighting below the benches. Construction taking place during the next several weeks will include the completion of the walls and benches, lighting improvements, installation of the sidewalk pavers on the north side and the construction of the enhanced pedestrian crosswalk. (June 16, 2020)

 Downtown Sidewalk Paver Restoration

Project Description

Stub Year 2020 marks the third year of a five-year Downtown Sidewalk Brick Paver Restoration Project. There is approximately 70,000 square feet of brick paver sidewalk in the downtown and this year’s program will restore an estimated 13,000 square feet on the north side of Park Avenue from Village Court to Vernon Avenue, the east side of Vernon Avenue from Park Avenue to Hazel Avenue, and the north side of Hazel Avenue from Vernon Avenue to Village Court. The scope of the work includes the removal of all brick pavers/border tiles, regrading of the stone sub-base and  resetting the brick pavers/border tiles including the replacement of any that are stained or cracked. The Village will be working with the contractor to limit the impact to businesses and patrons.

  • Total Project Cost: $105,000
  • Project ContractorA-1 Contractors, Inc.
  • Project Start Date: May 4, 2020
  • Project Completion Date: July, 2020
  • Project Manager: Donald Kirk, General Superintendent
  • Resident Impacts: Some intermittent loss of parking in the commuter lot.
  • Project Location Map: View location map
  • Initial Notification Letter: View letter here
  • Construction Update: The brick paver restoration has resumed after a two week pause. The project is approximately 70 percent completed. The project is expected to be completed in two weeks. (6/16/2020)


Commuter Parking Lot Lighting Improvements

Project Description

The second phase of an overall street light improvement plan in downtown Glencoe includes replacement of the street light poles and fixtures with new LED lamps in the southwest and southeast commuter lots. The new poles and fixtures will be consistent with the design of the streetlights throughout downtown, as well as with the new lights installed in the northwest commuter lot earlier this year.

  • Total Project Cost: $155,000
  • Project Contractor: Jasco Electric Corporation
  • Project Start Date: June 29, 2020
  • Project Completion Date: TBD
  • Project Manager: Donald Kirk, General Superintendent
  • Resident Impacts: Some intermittent loss of parking in the commuter lots.
  • Project Location Map: View location map
  • Initial Notification Letter: Pending
  • Construction Update: This project is currently paused while the department awaits the the delivery of the light poles, scheduled for the week of June 29. (6/16/2020)

Water Main Improvement Project

Project Description
The Stub Year 2020 Budget includes water main improvements on three streets: Forest Way Drive, Longwood Avenue and Hawthorn Avenue. The Forest Way Drive project will consist of the installation of 497 feet of twelve  inch water main and the replacement of water services from the water main to the b-box. The Longwood Loop Avenue project will include the installation of 296 feet of six inch water main and the replacement of water services from the main to the b-box. Lastly, 1,540 feet of water main will be replaced with an eight inch water main on Hawthorn Avenue and services will be replaced to the b-box.