>

Village Construction Projects

CIPLogoFINAL(Small)

Current Construction Projects 

Staff is busy coordinating with contractors to complete several capital improvement projects for 2021 as detailed in the Village's 10-Year Community Investment Program (CIP). As continue the construction season, stay tuned to the construction updates on this page, subscribe to Village eNews for timely updates as these projects progress. 

Look here for more information on regional construction projects being conducted by other agencies. 


 Downtown Sidewalk Paver Restoration

Project Description

Calendar Year 2020 marks the fourth year of a five-year Downtown Sidewalk Brick Paver Restoration Project. There is approximately 70,000 square feet of brick paver sidewalk in the downtown and this year’s program will restore an estimated 13,000 square feet on the north side of Park Avenue from Green Bay Road to Village Court, the east side of Village Court from Park Avenue to Hazel Avenue, the south side of Hazel Avenue from Vernon Avenue to Village Court, and Vernon Avenue from Hazel Avenue to Temple Court. The scope of the work includes the removal of all brick pavers/border tiles, regrading of the stone sub-base and  resetting the brick pavers/border tiles including the replacement of any that are stained or cracked. The Village will be working with the contractor to limit the impact to businesses and patrons.

  • Total Project Cost: $120,000
  • Project ContractorA-1 Contractors, Inc.
  • Project Start Date: April 2021
  • Project Completion Date: July, 2021
  • Project Manager: Donald Kirk, General Superintendent
  • Resident Impacts: Some intermittent loss of parking in the commuter lot.
  • Project Location Map: View location map
  • Initial Notification Letter: Pending
  • Construction Update: Pending

Sanitary Sewer Rehab-IICP (Area 2)

Project Description

The Village’s sanitary sewer system consists of 40 miles of sanitary sewer main, 1,042 manholes and eight lift stations. Repair and rehabilitation of the sanitary sewer collection system is an ongoing process which includes pipe replacement, lining and manhole repairs. As a requirement of the Metropolitan Water Reclamation District (MWRD) mandated Infiltration/Inflow Control Program (IICP) to eliminate inflow and infiltration (i/I) from sanitary sewer system, the Village has retained an engineering consultant. In 2021, this consultant will perform a detailed condition assessment investigation to identify defects in Area 2 of the sanitary sewer collection system and the results will be utilities to conduct sanitary sewer point repairs, sewer main lining and sanitary sewer manhole rehabilitation. (Improvements in Area 1 of the sanitary sewer collection system were completed in 2018 and 2019.)

  • Total Project Cost:$325,000
  • Project Contractor: TBD
  • Project Start Date: TBD
  • Project Completion Date: TBD
  • Project Manager: James Tigue, Village Engineer
  • Resident Impacts: TBD
  • Project Location Map: View location map
  • Initial Notification Letter: Pending
  • Construction Update: Pending

Residential Sidewalks

Project Description

The Village maintains over 73 miles of public sidewalk throughout the community. Each year, the Village assesses the condition of residential sidewalks and replaces them based on the structural condition of the concrete (cracking, spalling or deterioration), heaved or excessive sloping due to tree roots and poor drainage. The primary goal of the program is to maintain a safe and functional pedestrian sidewalk system. The residential sidewalk replacement program in the Village is managed through dividing the sidewalk system into three zones with each zone inspected on a three-year cycle. Identified sidewalk squares, together with reported hazard locations, comprise an annual targeted replacement program. In 2021 the focus on replacing deficient existing sidewalk in Area 3.

  • Total Project Cost:$200,000
  • Project Contractor: Schoeder & Schoeder Inc.
  • Project Start Date: May 2021
  • Project Completion Date: TBD
  • Project Manager: James Tigue, Village Engineer
  • Resident Impacts: Temporary sidewalk closures
  • Project Location Map: View location map
  • Initial Notification Letter: Pending
  • Construction Update: Pending

Continuous Cart Path

Project Description

The Glencoe Golf Club (GGC) has experienced two of the wettest seasons on record in 2018 and 2019. The golf course does not currently have continuous paths, which would allow the course to remain open for power golf carts during excessively wet weather conditions. The Glencoe Golf Club currently has cart paths adjacent to the tee and green areas but not in between these areas linking the holes. This year’s project will focus on connecting these points on holes #3, #4, #5 and #8 with approximately 3,400 linear feet of newly constructed cart paths.

  • Total Project Cost:$55,000
  • Project Contractor: TBD
  • Project Start Date: TBD
  • Project Completion Date: TBD
  • Project Manager: Dave Arden, Golf Course Superintendent
  • Construction Update: Pending

Driving Range Tee Expansion

Project Description

The Glencoe Golf Club (GGC) driving range currently offers 20 hitting stalls on all grass tees which is ideal for practicing with irons and wedges. Unfortunately, due to the location and limited footprint of the driving range, patrons are limited to hitting irons only and drivers/woods are prohibited.  To remedy the situation, the Glencoe Golf Club will be improving the driving range to allow for the full use of drivers and woods with the installation of netting along Westley Road. The project will also create a sledding hill at the back of the range.

  • Total Project Cost:$348,000
  • Project Contractor: TBD
  • Project Start Date: TBD
  • Project Completion Date: TBD
  • Project Manager: Dave Arden, Golf Course Superintendent
  • Notification Letter: Pending
  • Construction Update: Pending